Math, asked by magicleafs71padkp6, 1 year ago

150 labourers were engaged to finish a piece of job in a certain number of days 4 labourers dropped the second day , four labours dropped third day and so on. It takes 8 more days to finish the job now. Find the number of days in which the job was completed

Answers

Answered by vkarunya
0
Ans: 25

Suppose 1 worker does 1 unit work in a day

Assume 150 workers can finish the work in (n-8) days, if all workers work all the days.
Then, total work =150(n−8) ⋯(1)=150(n−8) ⋯(1)

Actually 150 workers work on day-1, 146 workers work on day-2, ... and work is completed in nn days. Therefore,
total work = 150 + 146 + ...  (nn terms)

This is an arithmetic progression with a = 150, d = -4. Therefore,
total work
=n2[2×150+(n−1)(−4)]=n2[300−4n+4]=n2[304−4n]=n(152−2n) ⋯(2)=n2[2×150+(n−1)(−4)]=n2[300−4n+4]=n2[304−4n]=n(152−2n) ⋯(2)

From(1) and (2)
150(n−8)=n(152−2n)75(n−8)=n(76−n)75n−600=76n−n2n2−n−600=0(n−25)(n+24)=0n=25150(n−8)=n(152−2n)75(n−8)=n(76−n)75n−600=76n−n2n2−n−600=0(n−25)(n+24)=0n=25

i.e., number of days in which the work was completed = 25

magicleafs71padkp6: Thank u so much