150 men can finish a piece of work in 12 days how many days will 120 men take to finish the same work
Answers
Answered by
1
Answer:
9.6days
Step-by-step explanation:
No.of men : No.of days :: No.of.men : No.of days
150:12::120:?
So,
12*120/150
=9.6