150 men can finish a piece of work in 12 days. How many days will 120 men take to finish the same work?
Answers
Answered by
8
*sigh*
if 150 does in 12 days one will take more time means,
12*150
then 120 will do it for,
cause, 12*150/120 = 150/10 = 15
15 days.
if 150 does in 12 days one will take more time means,
12*150
then 120 will do it for,
cause, 12*150/120 = 150/10 = 15
15 days.
Answered by
11
When men = 150, days taken =12
When men = 1 , days taken =150×12
When men =120, days taken = 150 ×12 ÷ 120 =15
HOPE IT HELPED