Math, asked by sumitkviisc, 1 year ago

150 men were hired to finish a construction. 150 men worked the first day,146 the second, 142 the third day and so on. If the work was completed with 7 day delay, in how many days would the work have been completed if 150 men worked every day


sumitkviisc: hi

Answers

Answered by ashim97
2

Let, 150 men would have completed the work in 'n' days working all days.

Now no. of men & no. of days are inversely proportional. So, we get,

150n = constant ----------->(1)

But, from 2nd day, 4 men left and so on and it took 8 days more than the normal to finish the work, ie, (n + 8) days. Consequently,

150 + 146 + 142 +.......to (n+8) terms = constant

Left hand side is an A.P, with 1st term =150, common difference = -4

So, using formula,

(n+8)*1/2*[2*150+(n+8-1)(-4)]= constant ------->(2)

From equations,

(n+8)[300+(n+7)(-4)]=300n

Solving the quadratic equation, we get,

n = 17, or -32(neglected)

Hence, work is completed in,

n+8

= 17 + 8

= 25 days

Pls, verify if it's correct. I ain't sure.

2.5k Views · · Answer requested by

Your feedback is private.

Is this answer still relevant and up to date?

Can 4 men complete a work in 12 days in as many days 12 workers can complete it?

If 24 men take 16 days to finish a work, then 1 man can finish in how many days?

How many days and hours a week do part time workers work?

12 workers take 12 days for complete one work. How many days does it take for this work by 8 workers?

What are the day-to-day work now?

A2A

Let x days be required to finish the work by 150 workers.

Therefore, total man days is 150x.

In 1 day, 1 person can finish 1/(150x) amount of work.

First day, 150 people work,

Total work done is 150/(150x)

Second day, 4 drop off, hence 146 work,

Total work done is 150/(150x) + 146/(150x)

This continues for (x+8) days.

Therefore,

150/(150x) + 146/(150x) + .... (x+8) terms = 1

(1/150x)*{150 + 146 + .... (x+8) terms} = 1

The numbers form an AP with n = (x+8) terms, a = 150 & d = -4

Sum of terms of an AP is given by

(n/2)*{2a + (n-1)d}

Here,

(1/150x) * [{(x+8)/2} * {2*150 + (x+8-1)*(-4)}] = 1

(1/150x) * [{(x+8)/2} * 2{150 + (x+7)*(-2)}] = 1

(1/150x) * [(x+8) * {150 + (-2x-14)}] = 1

[(x+8) * {150 -2x-14}] = 150x

[(x+8) * {136 -2x}] = 150x

136x -2x^2 + 1088 -16x -150x = 0

-2x^2 +1088 -30x = 0

x^2 + 15x - 544 = 0

(x+32)(x-17) = 0

x = -32 or x = 17

As x is no. of days, it cannot be negative.

Therefore, x = 17.

The no. of days to finish the work is x + 8 = 25 days.

2.7k Views · · Answer requested by

Your feedback is private.

Is this answer still relevant and up to date?

If I understood your question correctly, then 4 workers dropped from second day.

Let total days be 'N'.

Total work done = 150*N (man days)

Work done on first day = 150*1 = 150 (man days)

Work done by using 146 workers on second day = 146 man days

and so on.. for (N+8) days.

So 150*N = 150 + 146 + 142 + .....(N+8) terms........... + (150 - 4(N+8-1)) ..{A . P.}

150*N = 150(N+8) - {0 + 4 + 8 + 12 + ....... + 4(N+7)}

The bold region is in A. P. which has sum = (N+8)(4(N+7))/2

So

150*8 = 2(N+7)*(N+8) => N = 17, -32.

Actual expected days is 17 days but it is done in 25 days at dropping 4 on each day.

Note: Sorry for wrong answer earlier.


ashim97: welcome bro
Answered by darshana84
0

the answer of your question is 25 days

Similar questions