Math, asked by mohsinanjaana110, 23 hours ago

150 mens can complete a work in 5 days. After 15 days, 25 mens left the job in how many days will the remaining work be finished​

Answers

Answered by yogheswardharmarajan
1

Step-by-step explanation:

Okay

150 x 50 = 7500 output

therefore 150 X 15 = 2250

therefore new output is 7500 - 2250 = 5250

therefore 125 men X ? Days = 5250 output

therefore X = 42 days

plus 15 days already completed with full compliment of men

57 days in total

Mark me as brainliest

Answered by s21332
1

Answer: 57 days

Step-by-step explanation

150 x 50 = 7500 output

therefore 150 X 15 = 2250

therefore new output is 7500 - 2250 = 5250

therefore 125 men X ? Days = 5250 output

therefore X = 42 days

plus 15 days already completed with full compliment of men

57 days in total