150 mens can complete a work in 5 days. After 15 days, 25 mens left the job in how many days will the remaining work be finished
Answers
Answered by
1
Step-by-step explanation:
Okay
150 x 50 = 7500 output
therefore 150 X 15 = 2250
therefore new output is 7500 - 2250 = 5250
therefore 125 men X ? Days = 5250 output
therefore X = 42 days
plus 15 days already completed with full compliment of men
57 days in total
Mark me as brainliest
Answered by
1
Answer: 57 days
Step-by-step explanation
150 x 50 = 7500 output
therefore 150 X 15 = 2250
therefore new output is 7500 - 2250 = 5250
therefore 125 men X ? Days = 5250 output
therefore X = 42 days
plus 15 days already completed with full compliment of men
57 days in total