150. P is thrice as good workman as Q and is therefore able to finish the work in 60
days less than Q. Q can finish the work in.
(a) 220 days
(b) 25 days
(c) 90 days
(d) 33 days
Answers
Answered by
0
Answer:
90 days
Step-by-step explanation:
efficiency 3:1
time. 1:3
time 3-1 = 2
2-60
1-30
30×3= 90 days