15men can do a piece od work in 80 days .how lomg does it take to finish if 5 men are added
Answers
Answered by
3
Answer:
plz mark it brainliest
Attachments:
Answered by
2
Step-by-step explanation:
15 men - 80 days
1 men - 80*15
20 men -80*15/20
=60days