16)12 men, working 8 hours a day, complete a piece of work in 10 days. How
many men will require to complete the same work in 8 days, working 15
hours a day?
pls answer guys.....
Answers
Answered by
0
Answer:
8 men
Step-by-step explanation:
First you have to calculate units of work
W= Men×Days×Hours
W= 12×10×8= 960 units
Now to complete these 960 units in 8 days, while working 15 hours a day, the no. of men required will be= 960÷(15×8)= 8 Men
Answered by
1
Answer:
Total time to finish the work is10×8hours =80hours
80 hours required for 12 men
1 hour required for 12×80 men
15×8hours required for 12×80/15×8men
=8men
8 men will require to finish the work