16. 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.
Answers
Answer:
The time one girl alone finish the work in 140 days and one boy alone finish the work in 280 days.
Step-by-step explanation:
Let the time taken by girls be “x” days and the time taken by boys be “y” days.
So,
Work done by 1 girl in 1 day = 1/x
work done by 1 boy in 1 day = 1/y
According to the question, we can write the eq. as,
8/x + 12/y = 1/10 ............ (i)
and
6/x + 8/y = 1/14 .......... (ii)
Let’s consider u = 1/x & v = 1/y, so we can rewrite the eq, as,
8u + 12v = 1/10 ......... (iii)
and
6u + 8v = 1/14 ........... (iv)
Now, on multiplying eq. (iii) by 2 & eq. (iv) by 3 and subtracting the equations we get,
18u + 24v = 3/14
16u + 24v = 2/10
- - -
----------------------------
2u = 1/70
-------------------------
u = 1/140
Substituting the value of u = 1/140 in eq. (iii), we get
(8*1/140) + 12v = 1/10
⇒ 2/35 + 12v = 1/10
⇒ 12v = 1/10 – 2/35
⇒ 12v = [35 - 20] / [35*10]
⇒ v = 15 / [35*10*12]
⇒ v = 1/280
Since we have,
u = 1/x
⇒ 1/140 = 1/x
⇒ x = 140
and,
v = 1/y
⇒ 1/280 = 1/y
⇒ y = 280
Thus, one girl can alone complete the work in 140 days and one boy can alone complete the work in 280 days.
Hope it helps you