Math, asked by sonirajendra80059, 3 months ago

16. A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In how many days B alone will finish the work?​

Answers

Answered by nishanikumari53
1

Answer:

A, B, and C together take 10 days to complete a piece of work. Hence, A, B, and C together take 10 days to complete a piece of work.

Step-by-step explanation:

please mark me as brainlist

Answered by brainly1900
1

Answer:

A+B = 12

B+C = 15

A+C = 20

Lcm of (12,15,20) = 60

Efficiency is

A+B = 5

B+C = 4

A+C = 3

Total efficiency

2 (A+B+C) = 12

A+B+C = 6

Individual efficiency

A = 6 - 4 = 2

B = 6 - 3 = 3

C = 6 - 5 = 1

Individual time taken

A = 60/2 = 30 days

B =60/3 = 20 days

C = 60/1 = 60 days

hope this helps