16. A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In how many days B alone will finish the work?
Answers
Answered by
1
Answer:
A, B, and C together take 10 days to complete a piece of work. Hence, A, B, and C together take 10 days to complete a piece of work.
Step-by-step explanation:
please mark me as brainlist
Answered by
1
Answer:
A+B = 12
B+C = 15
A+C = 20
Lcm of (12,15,20) = 60
Efficiency is
A+B = 5
B+C = 4
A+C = 3
Total efficiency
2 (A+B+C) = 12
A+B+C = 6
Individual efficiency
A = 6 - 4 = 2
B = 6 - 3 = 3
C = 6 - 5 = 1
Individual time taken
A = 60/2 = 30 days
B =60/3 = 20 days
C = 60/1 = 60 days
hope this helps
please mark me as brainliest