16 farmers can harvest the crop in 9 days how many farmer are required to reap the same field in 4 days
Answers
Answered by
0
22 farmers are needed to reap the same field in 4 days
Answered by
0
Answer:
36 Farmers.
Step-by-step explanation:
16 farmer does work in 9days
now if farmers were 8 the work would have finished in 18 days,
Therefore, the work done by farmers is inversely proportional number of farmers.
So, 16×9 = 4× number of farmers
==> number of farmers = 16×9/4 = 36 farmers.
Hence to do the same work in 4 days
number of farmers required = 36