16 m of fencing was faid by 4 workers in 6 hours how many workers are required to lay 108 mof fencing in the same time​

Answers

Answered by PB1206
0

Answer:

27 workers

Step-by-step explanation:

Length of fencing = 16 m

number of workers = 4 workers

Time required = 6 hrs

Required length of fencing = 108 m

Total number of workers required = ?

Time required = 6 hrs

Therefore the number of workers required :

= (108 ÷ 16) × 4

= 6.75 × 4

= 27

Ans - 27 workers are required to lay 108m of fencing in 6hrs .