16 male and 20 female one work completed 25 days then 28males and 15 females howmeny days completed

Answers

Answered by manijha99
1
work is already done. No need to do it again
Answered by sid8126
2
So we can equate directly

16 men = 20 women

4 men = 5 women

5 women =4 men

1 women =4/5men

15 women=4/5×15

15 women = 12 men

=16 men complete a work in 25 days

1 men completes a work in =400 days

28men+15women = ?

28men+12men=40men

work in 25×16/40 = 10 days