16 man are employed to do a work in 20 days. At the end of 12 days the work is only half done. How many additional men should be employed to complete the work in the stipulated time?

Answers

Answered by Rishu1111111
4
the answer is the picture below
hope it helps
Brainelist it
Attachments:
Answered by vivek584
2
yes its ans is 4.......