16 man can do a piece of work in 30 days, Let’s find out how many days will 20 men finish the same work.
Answers
Answered by
0
Answer:
16 men needs 30 days
then 1 man will need more days to complete..
=16×30 days
Now 20 men will need 16×30/20 days
=24 days