Physics, asked by sudhakarm521, 4 months ago

16 men can complete a piece of work in 5 days. 20 women take 12 days to complete the same
piece of work. How many days will it take for 4 men and 8 women to complete the work?​

Answers

Answered by jayantdahiya
2

Answer:

4 men take 12.8 day

8 woman take 10 day

Explanation:

16 men take 5 days

first you have to find how many days 1 men take

1 men take 16/5 days

means 3.2 days

4 men take 4×3.2

12.8 days

20 woman take 12 days

1 woman take 20/12

means 1.25 day

8 woman take

8×1.25

10 days

Answered by anjumanyasmin
2

From the given question the correct answer is:

4 men take 12.8 day

8 woman take 10 day

Given:  

16 men take 5 days

20 womwn take 12 days.

To find :

4 mens =  ? days

8 mens =? days

16 men take 5 days  

first you have to find how many days 1 men take

1 men take=  16/5 days

means= 3.2 days

4 men take

=4×3.2

=12.8 days

hence ,4 men take 12.8 day

20 woman take 12 days

1 woman take =20/12

means= 1.25 day

8 woman take

=8×1.25

=10 days

hence ,20 womwn take 12 days.