Math, asked by mayamalhotra4426, 11 months ago

16 men can complete a work in 15 days . 24 children can do same work in 20 days . in how many days will eight men and 8 children together complete the work ?

Answers

Answered by Anonymous
4
16men-15days
24children-20days
1men-1
Similar questions