Math, asked by chandanashow26, 4 months ago

16 men can dig a pond in 21 days working 8 hours per day. If the same pond
be dug in 14 days working 6 hours per day, how many additional men be appointed
for this ?​

Answers

Answered by kp89bbu
2

Answer:

M1*D1*H1/W1=M2*D2*H2

Let the men be x

16*21*8=14*6*x

2688=84x

x=2688/84

x=32

Similar questions