16 men can do a piece of works 15 days if the men is increase by 50% then by what percent day be reduced to get the same work done
Answers
Answered by
0
Answer:
33.33%
Step-by-step explanation:
= 16; = 15
( × ) = ( × )
Men increased by 50%. So, is 50% more than of . So, 150% of .
150% of =
150% of 16 = (150/100) × 16 = 24 men
(16 × 15) = (24 × )
= (16 × 15) ÷ 24
= 10 days
So, 16 men can do a work in 15 days, and 24 men can do a work in 10 days. The reduced percentage of Day is,
15 days = 100%
10 days = ? %
= (10×100) ÷ 15
= 66.66 %
So, 100-66.66 = 33.33%
33.33% is the reduced percentage of number of days in same work done.