Math, asked by Sharmapriya5565, 2 months ago

16 men can do a piece of works 15 days if the men is increase by 50% then by what percent day be reduced to get the same work done

Answers

Answered by VivekNNV
0

Answer:

33.33%

Step-by-step explanation:

M_{1} = 16; D_{1} = 15

(M_{1} × D_{1}) = (M_{2} × D_{2})

Men increased by 50%. So, M_{2}  is 50% more than of M_{1}. So, 150% of M_{1}.

150% of M_{1} = M_{2}

150% of 16 = (150/100) × 16 = 24 men

(16 × 15) = (24 × D_{2})

D_{2} = (16 × 15) ÷ 24

= 10 days

So, 16 men can do a work in 15 days, and 24 men can do a work in 10 days. The reduced percentage of Day is,

15 days = 100%

10 days = ? %

= (10×100) ÷ 15

= 66.66 %

So, 100-66.66 = 33.33%

33.33% is the reduced percentage of number of days in same work done.