16 men can finish a piece of work in 49 days. 14 men started working and in 8 days they could finish certain amount of work. if it is required to finish the remaining work in 24 days, how many more men should be added to the existing workforce?
Answers
Answered by
15
1man 1day work = 1/16*49
14 men are worked for 8 days = (1/16*49) * 14* 8= 1/7
Remaining work = 6/7
Then , (6/7)/ 24 = 1/28
Required men =14
14 men are worked for 8 days = (1/16*49) * 14* 8= 1/7
Remaining work = 6/7
Then , (6/7)/ 24 = 1/28
Required men =14
riya609:
1/7 How did it come?
Answered by
4
Answer: 14 more men should be added to the existing workforce.
Step-by-step explanation:
Since we have given that
Number of men can finish a piece of work in 49 days = 16
Number of men started working = 14
In 8 days, they could finish certain amount of work.
Amount of work done by 14 men in 8 days will be
Remaining work is given by
So, using the "Time and work rule":
Hence, 28-14=14 more men should be added to the existing workforce.
Similar questions