16 men complete one-fourth of a work in 12 days. What is the additional number of men required to complete the work in 12 more days?
a. 48
Answers
Answered by
0
Answer:
48 men.
Step-by-step explanation:
If 16 people do 1/4th work in 12 days, they need 12*4=48 days to complete it.
Hence, one person can do whole work alone in 48*16=768 days.
Now considering 1/4th work is already done. We need to so remaining 3/4th in 12 days. If one person does it, he will need 768*3/4 = 576 days.
And no. of people required to do it in 12 days , 576/12 = 48 people