16 men finish one third work in 6 days
The number of additional men required
complete the job in next 6 days are
Answers
Answered by
6
Answer:
men. part. days
16. 1/3. 6
x. 2/3. 6
x=2/3/1/3x6/6.x16=32
Addl.men=32-16 =16 men
Answered by
1
Step-by-step explanation: