16 persons complete a job in 14 days. How
many days will 8 persons take to complete
the same job?
(a)28
(b)18
(c)7
(d)21
Answers
Answered by
2
Answer:
the answer is 7
please mark me brainliest
Answered by
2
Answer:
The answer is 28
Step-by-step explanation:
By M¹ D¹ = M² D²
=16*14=8*D² = 16*14/8
= D² = 28