16 workers 8 hours daily to complete work in 15 days.how much time will required for 10 workers working 4 hours daily to complete the work.
Answers
Answered by
2
Answer:
48
Step-by-step explanation:
Shortcut formula:
M1 * D1 * H1= M2 * D2 * H2
M = number of Men, D = number of days and H = Hours.
Place all the values in the given formula.
=> 16 * 15 * 8 = 10 * D2 * 4
=> 1920 = 40 * D2
=> D2 = 48 days.
Hence, the number of days = 48.
#Hope my answer helped you!