16 workers can finish a piece of work in 52 days.how many days will 13 workers take to finish this work
Answers
Answered by
6
let the work done be ' 1 '
let M1, M2 are the workers and D1 ,D2 are the days .
W1 ,W2 is work done . since the work done is same ,so then , W1 = W2 = 1
M1 = 16 , D1 = 52 , W1 = W2 = 1
M2 =13 ,D2 =?
now , according to the formula ,
M1 D1 W2 = M2 D2 W1
16 × 52 × 1 = 13 × D2 × 1
D2 = 16 × 52 / 13
D2 = 64 days
therefore , 13 workers will finish the same work in 64 days .
_______________________________
Your Answer : 64 days
_______________________________
let M1, M2 are the workers and D1 ,D2 are the days .
W1 ,W2 is work done . since the work done is same ,so then , W1 = W2 = 1
M1 = 16 , D1 = 52 , W1 = W2 = 1
M2 =13 ,D2 =?
now , according to the formula ,
M1 D1 W2 = M2 D2 W1
16 × 52 × 1 = 13 × D2 × 1
D2 = 16 × 52 / 13
D2 = 64 days
therefore , 13 workers will finish the same work in 64 days .
_______________________________
Your Answer : 64 days
_______________________________
Similar questions