1600 labourers can finish the construction of a school in 120 days. How many more labourers
needed to construct the school in 20 days
Answers
Answered by
13
Answer:
of units of work is 1600 × 120 ie 192000 units. To finish it in 20 days 192000÷20 or 9600 workers are required that is another 8000 labourers are required.
Step-by-step explanation:
Follow me
Answered by
0
Answer:
Total labours-1600
Total days-120
Now atq,
Construction of school-20 days
So,1600/20=80
80 labour's are needed to construct in 20 days.
Hope it helps you