161/2m is the length of public sewer line of the road . 7.5m construction take place in one day .so how many days required for total sewer line
Answers
Answered by
2
Answer:
12 days should be correct answer
Similar questions
Physics,
1 day ago
World Languages,
1 day ago
English,
3 days ago
English,
3 days ago
Biology,
7 months ago