164.
occurrence times of events
Backward pass calculations are done to find__ occurence times of event
a. Tentative
b. Definite
C.Latest
d. Earliest
Answers
Answered by
0
Backward pass calculations are done to find latest occurrence time in the event.
• Option “C” is correct i.e latest
• A backward pass in the area of project management states to the calculation of late finish dates and late start dates for the shares of schedule activities that have not been finalized.
• Backward pass signifies moving backward to the result to compute late start or to find if there is any bug in the activity.
Hope it helped...