1648 persons contract a brge 721 person build same 48 days how many days
SilverLightning123:
could u give the correct ques?
Answers
Answered by
2
by using inverse variation
721 person = 48 days
1648 person = ? days
721 x 48 = 1648 x y
y = 721 x 48
_______ = 21 days
1648
721 person = 48 days
1648 person = ? days
721 x 48 = 1648 x y
y = 721 x 48
_______ = 21 days
1648