168 men can do a piece of work in 14 days, how many men will do the same work in 42 days? show ur solution.
Answers
Answered by
6
Answer:
56 men
Step-by-step explanation:
168 men --> 14 days
1 men = 1/(14*168) days = 1/2352 days
2352 men --> 1 day
42 days --> 2352/42 = 56 men
Answered by
1
Given:
168 men can do a piece of work in 14 days.
To Find:
In 42 days, how many men can complete the same task?
Solution:
Let m represent the number of men required to complete the task in 42 days.
The formula that is used to find the required value is . Here, M, D, H, and W represents the number of men, days, hour, and work done by men and women.
From the information in the question, formulate an equation.
Simplify the obtained expression.
Thus, 56 men are required to complete the task in 42 days.