17. If 30 men can do a piece of work in 27 days. In how
many days can 18 men do another piece of work 3
times as great ?
(A) 45 days
(B) 135 days
(C) 100 days
(D) 125 days
Answers
Answered by
1
Answer is 45 days
The image solution is provided to u
with the help of it u will understand it well!!
HAVE A NICE DAY
AND STAY SAFE
Attachments:
Answered by
1
Answer:
135 days
Step by Step explaination:
Now, 30 men can do a piece of work in 27 days, ATQ, if the work gets 3 times, then 18 men can finish the work in how many days. Now, put the same unit on the same side. Hence, 18 men can finish the other work which is 3 times greater than previous work in 135 days