Math, asked by AliVatsal3386, 1 year ago

17 men can complete painting school building in 120 days. If the work has to be completed in 102 days, how many more men is required

Answers

Answered by khushiamitabh
6

Answer:


Step-by-step explanation:

120 days-17 men

1 day-17×120 men

102 days-17×120÷102

=20 men

Thus, 20 men can complete the work in 102 days.


Answered by shreya32457
8
THANKS FOR THE QUESTION !

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

=> THIS IS AN EXAMPLE OF INVERSE PROPORTION :

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

=> INVERSE PROPORTION MEANS ....

=> HERE ARE TWO QUANTITIES :

1 . MEN

2. DAYS

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

=> IF ONE QUANTITY INCREASES ANOTHER DECREASES .....

=> IF ONE DECREASES ANOTHER INCREASES

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

=> IN THE INVERSE PROPORTION PRODUCT IF THE TWO QUANTITIES IS CONSTANT....

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

=> 17 MEN * 120 DAYS = X MEN * 102 DAYS

=> X = 17 * 120 / 102

=> X = 20 MEN

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕

HOPE IT WILL HELP U ......

THANKS AGAIN.....

⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕⭕