17 men finish a work in 12 days. In how many days will 4 men finish the same work
This question is from ratio and proportion please answer correctly with full formula written
Answers
Answered by
3
answer=51
Step-by-step explanation:
let the no.of days be x
then by indefinite proportion,
17 × 12=4 × x
so, x=51 answer
Hope this will be helpful
Answered by
0
Given: 17 men finish work in 12 days.
To find: We have to find the number of days required to finish the work by 4 men.
Solution:
To determine the number of days we have to follow the below steps as follows-
If the number of men decreases the number of days to finish the work increases. Thus it follows an inverse relationship.
17 men can finish the work in 12 days.
4 men will finish the work in 17×12/4=51 days.
Thus 4 men will finish the work in 51 days.