17 trainess can do in do as much work as 4 experts a day. If 12 experts and 9 trainees 5 days to dig a pond. how many trainees will one need alongside 4 expet to dig a similar Pool in 15 day?​

Answers

Answered by abhi96255
0

3 trainees are required