17. Which of the following is a method of determining the critical path?
a. Complete Enumeration method
b. Critical Path determination method
c. Both a &b
d. Activity method​

Answers

Answered by sindhuganaseelan3
0

Answer:

The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. ... A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.

Explanation:

option (b)

Answered by siddhipatil0
0

Answer:

B.Critical Path determination method.