175 men can dig 3,150 m of canal in 12
days. How many men are required to
dig 3,900 m of the canal in 8 days?
Answers
Answered by
4
Answer:
= 3900 = 24. = 325. The number of men required = 325
Answered by
0
Answer:
Given that 175 men dig a canal 3150m in 36 days.
175=3150=36
?=3900=24
The number of men is required to dig a canal=
3150
(175×3900×36)
=
75600
24570000
Step-by-step explanation:
Right Answer is: C
Number of man days is directly proportional to the length of the canal dug. Hence, 325 men are required to dig a length of 3900 m in 24 days.