175 men can dig a canal 3150 m long in 36 days.How many men are required to dig a canal 3900 m.long in 24 days?
Answers
Answered by
0
Answer:
Canal dig in one day = 3150÷175
= 18m
x1 y1 =x2 y2
175 multiply 36=x multiply 24
Step-by-step explanation: