Math, asked by akhilaafroz646, 5 months ago

175 men can dig a canal 3150 m long in 36 days. How many men are required to dig a
canal 3900 m. long in 24 days?​

Answers

Answered by FairyLight
39

Answer:

\boxed{\fcolorbox{black}{pink}{Solution}}

\boxed{\fcolorbox{black}{pink}{Given}}

  • In 36 days 175 men dig 3150 m long canal.
  • one man in one day digs 3150/(36×175) m long canal.
  • one man in 24 days can dig (3150×24)/(36×175) m long canal.
  • to dig 3900 m long canal in 24 days ,no of men is to be provide =3900÷{(3150×24)/(36×175)}

\boxed{\fcolorbox{black}{pink}{Equation}}

=(3900×36×175)/(3150×24)

=(78×50×12×3×175)/(63×50×12×2)

=(78×3×175)/(63×2)

=(39×175)/(21)

=(13×175)/7

=13×25

\pink{=325}

\boxed{\fcolorbox{black}{pink}{Hence, }}

325 men are required.

Answered by BrainBuildingAcademy
2

Step-by-step explanation:

Men1 × days1 = Men2 × days2

Work1 Work2

note - the one and two are in subscript

175 × 36 = M × 24

3150 3900

M = 175 × 36 × 3900

3150 × 24

M = 325 mens

1-

You can ask me maths questions personally by following me on brainly. I will answer questions of class 9, 10, 11 and 12 whenever i came online.

2-

You can thank me by subscribing my youtube channel "Brain Building Academy". It give benifits to class 9 & 10 mathematics students.If you subscribe my channel i will follow you on brainly. Thank you all have a nice day.

Similar questions