175 men can dig a canal 3150 m long in 36 days. How many men are required to dig a
canal 3900 m. long in 24 days?
Answers
Answered by
39
Answer:
- In 36 days 175 men dig 3150 m long canal.
- one man in one day digs 3150/(36×175) m long canal.
- one man in 24 days can dig (3150×24)/(36×175) m long canal.
- to dig 3900 m long canal in 24 days ,no of men is to be provide =3900÷{(3150×24)/(36×175)}
=(3900×36×175)/(3150×24)
=(78×50×12×3×175)/(63×50×12×2)
=(78×3×175)/(63×2)
=(39×175)/(21)
=(13×175)/7
=13×25
325 men are required.
Answered by
2
Step-by-step explanation:
Men1 × days1 = Men2 × days2
Work1 Work2
note - the one and two are in subscript
175 × 36 = M × 24
3150 3900
M = 175 × 36 × 3900
3150 × 24
M = 325 mens
1-
You can ask me maths questions personally by following me on brainly. I will answer questions of class 9, 10, 11 and 12 whenever i came online.
2-
You can thank me by subscribing my youtube channel "Brain Building Academy". It give benifits to class 9 & 10 mathematics students.If you subscribe my channel i will follow you on brainly. Thank you all have a nice day.
Similar questions