175 men can dig a canned 3150 m long in 36 days How many men can be required to dig a canned 3900 m long in 24 days
Answers
Answered by
1
Step-by-step explanation:
Answer Expert Verified
= 3900 = 24. = 325. The number of men required = 325. Hope this helps!
Answered by
0
Answer:
Step-by-step explanation:
by unitary method
175 = 31500 = 36
? = 3900 = 24
24570000 /75600
after cancelling zeros and simplifying
no. of men = 245700/756
= 325 men