176 workers can build a flyover in 53 days. How many workers needed to construct that flyover in 44 days ?
Answers
Answered by
2
Answer:
220
Step-by-step explanation:
The number of workers are inversely proportional to the no. of days.
Therefore,55×176÷44=x
where,x=The no. of workers