18. 40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days ?
Answers
Answered by
1
Answer:
65 men will be needed
Step-by-step explanation:
Number of men needed to finish a piece of work in 26 days = 40
Number of men needed to finish it in 1 day = 26 x 40 = 1040 (less days means more
men)
Number of men needed to finish it in 1040/16
= 65