18 boys can do a work in 24 days. In how many days can 27 boy do the same work
Answers
Answered by
1
One boy can do the work in 18*24 days
So 27 boys can do it in
18*24/27 days
= 16 days
So 27 boys can do it in
18*24/27 days
= 16 days