18 labourers can complete a durga Puja pandal in 1 month 6 days. How many more labourers is required to complete
it in 27 days
Answers
Answered by
1
Answer:
6 more labourers needed
Step-by-step explanation:
18 labourers complete a Durga Pooja in 1 month 6 days =36 days
18+x labourers can complete in 27 days
if the labourers increase the days decrease so it is inverse proportion
xy=k therefore 18*36=(18+x)*27
18+x=18*36/27(now simplify)
18+x=24 labourers
x=6 more labourers
Answered by
1
Answer:
Here is ur answer
Step-by-step explanation:
PLEASE MARK AS BRAINLIEST