18 men can complete a piece of work in 28 days. In how many days will 21 men complete the same piece of work?​

Answers

Answered by Eline75
67

 \huge \tt \:  \red Heya!

So let's solve this problem.

  • No.of men who completes the work in 28 days=18 men

  • To Find:In how many days will 21 men complete the same piece of work?

  • So,
  •   \sf\implies \: 28 \times 18 = 504
  •  \sf \implies \frac{504}{21}  = 24

•So it will take 24 days for 21 men to complete the work.

_________________________

Answered by nihasrajgone2005
4

\huge\red{A}\pink{N}\orange{S} \green{W}\blue{E}\gray{R} =

So let's solve this problem.

  • No.of men who completes the work in 28 days=18 men
  • To Find:In how many days will 21 men complete the same piece of work?

So,

  • \sf\implies \: 28 \times 18 = 504⟹28×18=504</li></ul><p></p><ul><li>\sf \implies \frac{504}{21} = 24⟹ </li></ul><p>21</p><p>504</p><p></p><p> =24

    •So it will take 24 days for 21 men to complete the work.