Math, asked by dibyajyotiprust5827, 1 year ago

18 men can complete a project in 30 days and 16 women can complete the same project in 36 days. 15 men start working and after 9 days they are replaced by 18 women. in how many days will 18 women complete the remaining work? (a) 20 (b) 30 (c) 26 (d) 28 (e) 24

Answers

Answered by AdityaKashyap458
7
1 man's work in one day= 1/(18*30)=1/540
1 woman's work in one day=1/(16*36)=1/576
work by 15 men in 9 days=15*9/540=1/4
remaining work= 1-1/4=3/4
18 women's work on one day= 18/576=1/32
time taken to complete the job= (3/4)*32=24 days
Answered by AneesKakar
0

18 women will complete the remaining work in (e) 24 days.

Given: 18 men can complete a project in 30 days and 16 women can complete the same project in 36 days. 15 men start working and after 9 days they are replaced by 18 women.

To Find: no. of days taken by 18 women to complete the remaining work.

Solution: Let work be done by 15 men in 9 days = W_2

\frac{M_1D_1}{W_1} =\frac{M_2D_2}{W_2}

\frac{18(30)}{1}=\frac{15(9)}{W_2}

W_2 = \frac{15(9)}{18(30)} = \frac{1}{4}

Remaining work = 1-\frac{1}{4} = \frac{3}{4}

16 women can complete the same project in 36 days, \frac{M_1D_1}{W_1}= \frac{M_2D_2}{W_2}

\frac{16(36)}{1}  = \frac{18(D_2)}{3/4}

⇒18 × D_2 =  \frac{3}{4} × 16 × 36

D_2= 24 days.

So, 18 women will complete the remaining work in (e) 24 days.

#SPJ3

Similar questions