18 men can do a piece of work in 10 days. How many less men are required if the work is to be completed in 15 days? . A hostel had ration for 60
Answers
Question :-
18 men can do a piece of work in 10 days. How many less men are required, if the work is to be completed in 15 days ?
Given that,
18 men can do a piece of work in 10 days.
Now, we have to find, how many less men are required if the work is to be completed in 15 days.
Let suppose that x less men are required.
So, it means 18 men can do a piece of work in 10 days and 18 - x men can completed the work in 15 days.
As, less men do a piece of work, so more days are needed to complete the work.
It means, number of days and number of men are inverse variation..
So,
So, using law of inverse variation, we have
So, it means 6 men less are required to complete the work in 15 days.
Basic Concept Used :-
Inverse Variation :- Two variables x and y are said to be in inverse or indirect Variation, if there is increase in x, then there is decrease in y or if there is decrease in x, then there is increase in y.