18 men can do a work in 25 days In how many days will 9 men do the same work?
Answers
Answered by
2
Answer:
50 days
Step-by-step explanation:
18/9 = 2
given
18 men = 25 days
hence
9 men take double days to complete work
therefore
25 × 2 = 50 days
Answered by
2
Answer:
If 18 people can do a work in 25 days then in how many days will 9 men's do the same work ?
if 18 is equal to 25 then
9×2=18 then 18=25 9=50
So the answer is 50 the 9 men's will take 50 days to do the work