18 men do a work in 15 days .in how many days will 60 men complete twice the

Answers

Answered by genius150809
4

Answer:

9 days

Step-by-step explanation:

18 men can do in 15 days

1 man can do it in 18 x 15=270 days

1 man can do twice work in 540 days

60 men can do twice work in 540/60 days= 9 days