18 men take 20 days to complete a piece of work how many days will it take 24 men to complete the same piece of work
Answers
Answered by
0
Step-by-step explanation:
20 men —30 days
1 man - 30*20 days=600 days
25 men=600/25 days
=24 days
So 25 men require 24 days to complete that job.
Answered by
2
Step-by-step explanation:
18 men —20 days
1 man - 20*18 days=360 days
24 men=360/24 days
=15 days
So 24 men require 15 days to complete that job.