18 people complete work in 12 days. They work for 6 days. After that 4 people added. So now time taken to complete the remaining work is -
Answers
Answered by
29
let 1 men does 1 unit of work per day
Total work: 18×12=216 units
6 days work of 18 men
=18×6=108 units.
work lelt =216- 108=108 units
After 6 days 4 men jøin. so total men is 22 men (18+4) they will do 22 unit of work per day
Now,
remaining work completed in